Start with available cash and obligations
Confirm bank balances and obligations already incurred. List upcoming payments: suppliers, delivery, advertising, rent, payroll, taxes, debt and other business expenses.
Show restrictions on cash use and the agreed reserve separately. A projected marketplace receipt remains an expectation until the money actually arrives.
Break purchases down by payment dates
Record the batch price and dates for advances, final settlement, delivery and other related payments. Staged and single payments create different pressure on cash.
Compare these dates with expected marketplace receipts and other obligations. Daily or weekly forecasts often help operational decisions while retaining individual transaction detail.
Compare several scenarios
Use agreed assumptions for sales, payouts, expenses and timing in the base case. Then test later receipts or sales below expectations.
Compare purchase volume, payment dates and terms agreed with the supplier. Change assumptions explicitly so it is clear which condition creates the shortfall and what needs discussion.
Find the shortfall date, not just the month-end total
A positive month-end balance does not rule out a mid-period shortage. For each date, calculate from the opening balance, expected receipts and planned payments.
If forecast cash falls below the agreed reserve, review the plan. Options may concern payment timing, purchase volume or financing. Check counterparty agreements and financing terms separately.
Replace forecasts with actuals
After receipts and payments, update the forecast using actual data. Explain whether variances arose from sales volume, payout timing, expenses or an initial assumption.
Purchasing planning then becomes part of regular financial support. The owner has a reasoned basis for decisions and understands their dependencies.
Worked example
Illustrative example, RUB thousands. Amounts are hypothetical and explain the method, not client results.
| Date and transaction | Option A: full payment on Thursday | Option B: payment in two stages |
|---|---|---|
| Monday: opening cash | 200 | 200 |
| Wednesday: obligations of 100 | 100 | 100 |
| Thursday: supplier payment of 600 or 100 | -500 | 0 |
| Friday: receipt of 500; option B also pays the remaining 500 | 0 | 0 |
Both options end with zero cash. Option A creates a Thursday shortfall of 500; option B does not. Rescheduling or splitting payments requires agreed supplier terms.
Checklist
- Confirm the opening cash balance.
- List obligations by date.
- Break purchases into payment stages.
- Test delayed receipts and changes in sales.
- Identify potential shortfall dates.
- Update forecasts with actuals.